|
HOME
EVENTS & MEETINGS
GET INVOLVED / WATERSHED RESOURCES
VOLUNTEER WATER MONITORING PROGRAM
NEWSLETTER
WATERSHED NEWS
PLANS, MAPS, PUBLICATIONS
SWCD STAFF
GROUPS:
EUCLID CREEK WATERSHED COUNCIL
FRIENDS OF EUCLID CREEK
Support Us
PROJECTS:
Cleveland WPC Green Infrastructure
East Branch Dam Removal
Euclid Creek Tunnel
Mayfield Hts Green
Infrastructure
South Euclid Nine Mile Wetland
Wildwood Wetland Restoration /
Lacustrine Refuge Project
| |
EUCLID CREEK WATERSHED PROGRAM
Euclid Creek East Branch Dam Removal and
Stream Restoration Project
Euclid Creek Metroparks Reservation, Euclid, Ohio
The Euclid Creek East Branch Dam
was located in the Euclid Creek Watershed on the East Branch of Euclid Creek, a
tributary to Lake Erie that is heavily urbanized and affected by urban runoff
and habitat degradation. The dam was located near the confluence of the East
Branch and the Euclid Creek mainstem in the Euclid Creek Metropark Reservation.
Highland Road crosses the East Branch on a high bridge over the dam.
The dam was removed in December
2010. The low head dam that was constructed in the early 1930's to impound water
for swimming at a YMCA camp and had not served this or any other essential
purpose in decades. The original pool behind the dam had completely filled with sediment.
The dam was approximately 6 feet high and constructed of concrete, and was an
impediment to fish migration upstream from the mainstem of Euclid Creek.
The dam and abutments
were removed and 704 linear feet (lf) of stream was restored to a more natural grade and geometry. The goals of this
project were to: 1) Reintroduce and re-establish native fish species; 2) Increase
recreational fishing opportunities; 3) Restore aquatic habitat diversity to the
watershed; 4) Restore natural flow in the lower reaches of the watershed; 5)
Provide fish passage to the upper reaches of the East Branch to further enhance
the health of this sub-watershed; and 6) Assist in restoring Euclid Creek to
reach State of Ohio water quality attainment standards.
| Click image below to see video of dam removal,
December 2010 |
|
 |
Project
Partners:
ODNR,
Divisions of Fish and Wildlife and Soil & Water, City of Euclid, Cleveland
Metroparks, Cuyahoga County Engineer, Cuyahoga Soil & Water Conservation
District, Ohio EPA, Northeast Ohio Regional Sewer District, and Friends of
Euclid Creek.
Land Owner: Cleveland Metroparks
Grants Manager: Cuyahoga Soil & Water
Conservation District
Design Consultant:
Burgess & Niple
Construction Management Entity:
Northeast Ohio Regional Sewer District
Project Costs:
Design and Engineering
$135,125
Construction
$542,585 (includes construction administration
and oversight costs)
$677,710
Project Funding:
For Design and Engineering:
$30,100 US
Fish & Wildlife Service, Midwest Region, Fish Passage Program
$27,000
ODNR, Division of Wildlife
$23,000
ODNR, Division of Wildlife through USFWS
For Construction:
$300,000
Ohio EPA, Water Resource Restoration Sponsor Program (WRRSP) (as match for Ohio
EPA 319 Program)
$235,428
Ohio EPA 319 Program

Aerial Location Map
Design Details:
The
graphic below shows a plan view of the dam removal and stream restoration
project, designed by consultant Burgess & Niple.
The engineering was more
complicated than most low-head dam removal projects because Highland Road, a
major County roadway, travels over this section of Euclid Creek. The footers of
the bridge were just upstream of the dam and required careful engineering to
keep the roadway overhead stable. In addition, urban streams experience
‘flashy flows’ in storms, meaning that water rises rapidly and quickly causing
major erosion and damage to bug and fish habitat. Therefore the design had
to take into account these unpredictable water fluctuations.
The design incorporated
natural stream design,
mimicking the riffle, run and pool geometry of unaltered natural streams. The
first step in the project was to remove the dam, a 6 foot tall concrete
structure. The second step was installing three structures which include placing
large stones in the stream to direct flow, slow flow down, prevent erosion, and
protect the bridge piers. Two
cross
veins (show in
yellow
in the graphic below)
control the stream grade, dissipate the energy of the water, and direct the
water flow to the center of the stream away from the bridge footers. A
gabion
mattress (green
shaded area) was
installed below the bridge to protect the bridge footers and to prevent
degradation of the bedrock below. A
boulder-cobble run (blue
shaded structures)
acts as grade control to mimic existing run features found in natural
streams and incorporates low flow pathways and resting pools to allow small
fish to move upstream. Excavated
scour
pools (pink
shaded areas) also mimic the slow moving pools in natural streams to allow fish to rest and
move upstream. Excavated material behind the dam was allowed to flow
downstream as the stream has been starved of this important sediment for years.
Last of all, native plants were planted along the stream to provide habitat
for fish and bugs.


Project Publications & News:
Euclid Creek Newsletters articles about project:
Articles about Project:
Project Monitoring:
Project Resources:
Project Status:
Bid/Construction Schedule:
- Project to Bid:
Tuesday, July 6, 2010
- Pre-Bid Conference Info.
Mtg.: Wednesday, July 14 at 10:00am - Environmental Maintenance Services
Center - 4747 E. 49th St., Cuyahoga Hts., OH 44125
- Bid Proposal Due Date:
Friday, August 6, 2010
- Award: Thursday,
September 16, 2010 at
NEORSD Board Meeting - to Great Lakes Construction Company of Hinckley,
Ohio.
- Pre-Construction Meeting: Tuesday,
October 12, 2010 at 1:00pm - Environmental Maintenance Services Center - 4747
E. 49th St., Cuyahoga Hts., OH 44125
- Construction Start Date: October 18,
2010
- October to November: Construction
staging area and access roads were prepared; a stream pump around system was
installed so construction could occur in dry weather conditions; and the
gabion mattress baskets were started.
- December 7, 2010: the East
Branch dam was removed
- Late
December: remainder of gabion mattress installed, cross vane and boulder
cobble run structures completed (see 'Design Details' section above for
explanation of structures and their function in the natural stream design)
- Spring 2011: plantings to complete
riparian restoration, Metroparks' staff designed and installed interpretive signage,
fencing and park benches
at Upper Highland Picnic Area overlook.
- Dam Removal Celebration: Thursday,
April 21, 2011 from 5:00-7:00pm - Euclid Creek Reservation - Upper Highland
Reservable Picnic Area -
Event Agenda
 
 
Jobs
Created/Retained due to Project = 36-38
-
20 people worked on design, surveying, field
admin and constructions services
-
11 people worked on the construction portion
of the project
-
5-7 will work on the riparian plantings in
2011
Construction Photos:

For more
information, please contact Claire Posius, Euclid Creek Watershed Coordinator,
216-524-6580x16 or email cposius@cuyahogaswcd.org.
Euclid Creek Homepage
|